Schedule

Announced and approvedMar 4, 2021
202120222023202420252026
Built

Approved 3 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Dec 18, 2023(actual)
Construction end
Mar 24, 2026(actual)

Against the original forecast

  • Construction start22 months lateforecast Feb 22, 2022
  • Construction end4 months lateforecast Nov 28, 2025