Construction of a new pavilion for the Centre communautaire de loisirs Claude-Nault at Parc Boisbriand

Drummondville, Quebec

completeRecreationCCRIS
Federal contribution
$860,453
Federal share29%

of $2.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 28, 2021
2021202220232024
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Sep 1, 2022(actual)
Construction end
Dec 20, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 1, 2022
  • Construction end4 months lateforecast Sep 1, 2023