Provincial Road 280: Grading
Federal contribution
$1.7M
$1,653,045
Federal share50%
of $3.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 27, 2021
2021
Built
Approved 8 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Province of Manitoba
- Construction start
- Mar 16, 2021(actual)
- Construction end
- Oct 1, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast Feb 1, 2021
- Construction end2 months lateforecast Aug 1, 2021
Also in Thompson
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58102 in the federal list. How to read these figures.