College of the North Atlantic (St. Anthony Campus) Lighting Upgrade

St. Anthony, Newfoundland and Labrador

completeEducation, Training and ChildcareCVRIS
Federal contribution
$72,575
Federal share80%

of $90.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 12, 2021(actual)
Construction end
Aug 17, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Mar 15, 2021
  • Construction end3 months earlyforecast Nov 30, 2021

Also in St. Anthony

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58285 in the federal list. How to read these figures.