Schedule
Announced and approvedApr 14, 2021
202120222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Construction start
- Aug 7, 2023(actual)
- Construction end
- Aug 18, 2023(actual)
Against the original forecast
- Construction start8 months lateforecast Dec 5, 2022
- Construction end8 months lateforecast Dec 23, 2022