Holy Spirit High School Gym Floor Replacement

Conception Bay South, Newfoundland and Labrador

completeRecreationCVRIS
Federal contribution
$128,206
Federal share80%

of $160.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 14, 2021
2021
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 15, 2021(actual)
Construction end
Nov 13, 2021(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 5, 2021
  • Construction end2 months lateforecast Aug 31, 2021