Back to projects

Corner Brook Arts and Culture Center Heating and Lighting Upgrade

Corner Brook, Newfoundland and Labrador

completeVentilationCVRIS
Federal contribution
$44,611
Federal share80%

of $55.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
202120222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jan 16, 2023(actual)
Construction end
May 15, 2023(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Nov 30, 2022
  • Construction end3 months lateforecast Feb 1, 2023

Also in Corner Brook