Corner Brook Arts and Culture Center Heating and Lighting Upgrade
Corner Brook, Newfoundland and Labrador
Federal contribution
$44,611
Federal share80%
of $55.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
202120222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Construction start
- Jan 16, 2023(actual)
- Construction end
- May 15, 2023(actual)
Against the original forecast
- Construction start7 weeks lateforecast Nov 30, 2022
- Construction end3 months lateforecast Feb 1, 2023