Rocky View HVAC Upgrades to City Hall

Rocky View County, Alberta

completeVentilationCVRIS
Federal contribution
$94,996
Federal share80%

of $118.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
Built

Approved 6 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 15, 2021(actual)
Construction end
Jun 30, 2021(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast Apr 1, 2021
  • Construction end4 weeks lateforecast May 31, 2021

Also in Rocky View County

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58485 in the federal list. How to read these figures.