St Albert Active Transportation Plan
Federal contribution
$878,906
Federal share80%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of St. Albert
- Construction start
- May 11, 2021(actual)
- Construction end
- Aug 24, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast Apr 1, 2021
- Construction end4 months earlyforecast Dec 31, 2022
Also in St. Albert
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58487 in the federal list. How to read these figures.