St Albert Larose Park Court Refurbishment

St. Albert, Alberta

completeActive TransportationCVRIS
Federal contribution
$284,325
Federal share73%

of $390.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2021
Built

Approved 6 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of St. Albert
Construction start
Jun 17, 2021(actual)
Construction end
Sep 1, 2021(actual)

Against the original forecast

  • Construction start3 months lateforecast Apr 1, 2021
  • Construction end2 months earlyforecast Oct 31, 2021

Also in St. Albert

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58491 in the federal list. How to read these figures.