St Albert Kingsmeade Park
Federal contribution
$1.7M
$1,698,695
Federal share64%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
2022
Built
Approved 2 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of St. Albert
- Construction start
- May 18, 2021(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction start7 weeks lateforecast Apr 1, 2021
- Construction end7 months lateforecast Nov 30, 2021
Also in St. Albert
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58493 in the federal list. How to read these figures.