Spruce Grove Fleet Shop Expansion
Federal contribution
$80,000
Federal share46%
of $175.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
2022
Built
Approved 6 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Spruce Grove
- Construction start
- Nov 8, 2021(actual)
- Construction end
- May 18, 2022(actual)
Against the original forecast
- Construction start10 months lateforecast Jan 7, 2021
- Construction end3 weeks lateforecast Apr 30, 2022
Also in Spruce Grove
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58509 in the federal list. How to read these figures.