Installation of Classroom Unit Ventilation
Federal contribution
$160,000
Federal share80%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
2022
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Algonquin and Lakeshore Catholic District School Board
- Construction start
- Aug 9, 2021(actual)
- Construction end
- Jun 30, 2022(actual)
Against the original forecast
- Construction start6 months lateforecast Feb 18, 2021
- Construction end6 months earlyforecast Dec 31, 2022
Also in Greater Napanee
- Town of Greater Napanees Water Pollution Control Plant Expansion$14.0M
- HVAC/Ductwork/BAS Installation; Automatic Door Operators; Handwashing Station; Bottle Fill Station$2.1M
- Ductwork and Classroom Unit Ventilation Installation$760.0K
- Ductwork Installation; HVAC Installation; Bottle Fill Station$578.0K
- Rehabilitation of Thomas Street$463.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58593 in the federal list. How to read these figures.