Red Deer Waskasoo Creek Scour and Erosion
Federal contribution
$81,840
Federal share80%
of $102.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
2022
Built
Approved 2 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Red Deer
- Construction start
- Apr 1, 2022(actual)
- Construction end
- May 31, 2022(actual)
Against the original forecast
- Construction end7 months earlyforecast Dec 31, 2022