Red Deer Community Infrastructure Preservation
Federal contribution
$1.4M
$1,408,466
Federal share80%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
2021202220232024
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Red Deer
- Construction start
- Mar 15, 2021(actual)
- Construction end
- Oct 15, 2024(actual)
Against the original forecast
- Construction start4 weeks lateforecast Feb 15, 2021
- Construction end3 months earlyforecast Dec 31, 2024