Red Deer 77 Street Sidewalk/Trail
Federal contribution
$1.6M
$1,553,991
Federal share80%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
2022
Built
Approved 4 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Red Deer
- Construction start
- Mar 24, 2022(actual)
- Construction end
- Oct 30, 2022(actual)
Against the original forecast
- Construction end11 months earlyforecast Oct 15, 2023
Also in Red Deer
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58742 in the federal list. How to read these figures.