Red Deer Westerner Storm Water Pond Reconstruction
Federal contribution
$1.7M
$1,691,644
Federal share80%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 16, 2021
202220232024
Built
Approved 2 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Red Deer
- Construction start
- Nov 1, 2022(actual)
- Construction end
- Jul 31, 2024(actual)
Against the original forecast
- Construction start6 months lateforecast May 1, 2022
- Construction end2 weeks lateforecast Jul 15, 2024