Chiller Replacement
Federal contribution
$306,577
Federal share76%
of $403.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Drummondville
- Construction start
- Jun 12, 2023(actual)
- Construction end
- Sep 17, 2024(actual)
Against the original forecast
- Construction end2 months lateforecast Jul 19, 2024
Also in Drummondville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58869 in the federal list. How to read these figures.