Grande Prairie Hillside Paths and Trees
Federal contribution
$136,664
Federal share79%
of $173.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 17, 2021
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Grande Prairie
- Construction start
- Aug 5, 2021(actual)
- Construction end
- Aug 14, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast May 18, 2021
- Construction end2 weeks earlyforecast Aug 31, 2021
Also in Grande Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58878 in the federal list. How to read these figures.