Grande Prairie Maskwôtêh Bridge

Grande Prairie, Alberta

completeActive TransportationCVRIS
Federal contribution
$176,000
Federal share80%

of $220.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 17, 2021
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Grande Prairie
Construction start
Aug 15, 2021(actual)
Construction end
Oct 29, 2021(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Dec 15, 2021