Grande Prairie Playground Upgrades and Surfacing
Federal contribution
$240,000
Federal share80%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 17, 2021
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Grande Prairie
- Construction start
- May 31, 2021(actual)
- Construction end
- Aug 4, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2021
- Construction end4 months earlyforecast Nov 30, 2021
Also in Grande Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58880 in the federal list. How to read these figures.