Grande Prairie Tree Replacements
Federal contribution
$108,160
Federal share80%
of $135.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 17, 2021
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Grande Prairie
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Jul 21, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast May 1, 2021
- Construction end3 months earlyforecast Oct 31, 2021
Also in Grande Prairie
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58885 in the federal list. How to read these figures.