Repair and replacement of flat roofs in block A

Saint-Jérôme, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$800,000
Federal share80%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2022(actual)
Construction end
Apr 26, 2024(actual)

Against the original forecast

  • Construction start5 months lateforecast Jun 2, 2022
  • Construction end4 months lateforecast Dec 31, 2023