Repair and replacement of flat roofs in block A
Federal contribution
$800,000
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux des Laurentides
- Construction start
- Nov 1, 2022(actual)
- Construction end
- Apr 26, 2024(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 2, 2022
- Construction end4 months lateforecast Dec 31, 2023
Also in Saint-Jérôme
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58889 in the federal list. How to read these figures.