Renovation of roofs

Saint-Jérôme, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$749,301
Federal share67%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep de Saint-Jérôme
Construction start
May 17, 2021(actual)
Construction end
Oct 25, 2021(actual)

Against the original forecast

  • Construction end2 months lateforecast Aug 20, 2021