Renovation and upgrading of elevators in Pavilions B and D

Saint-Jérôme, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$394,370
Federal share80%

of $493.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep de Saint-Jérôme
Construction start
Apr 25, 2022(actual)
Construction end
Sep 23, 2022(actual)

Against the original forecast

  • Construction end3 months lateforecast Jul 1, 2022

Also in Saint-Jérôme

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59055 in the federal list. How to read these figures.