Replacement of 161 ventilation units for bedrooms (HEPA filters)
Federal contribution
$658,400
Federal share80%
of $823.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
2024
Built
Approved 18 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux des Laurentides
- Construction start
- Feb 24, 2023(actual)
- Construction end
- Apr 30, 2024(actual)
Against the original forecast
- Construction start6 weeks lateforecast Jan 15, 2023
- Construction end2 months earlyforecast Jun 30, 2024
Also in Saint-Jérôme