Upgrades to the gym and locker rooms

Rimouski, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$168,000
Federal share42%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 20, 2021(actual)
Construction end
May 13, 2022(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Aug 15, 2021
  • Construction end4 months lateforecast Jan 18, 2022

Also in Rimouski

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58910 in the federal list. How to read these figures.