Upgrades to the gym and locker rooms
Federal contribution
$168,000
Federal share42%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre Intégré de santé et des services sociaux du Bas-Saint-Laurent
- Construction start
- Sep 20, 2021(actual)
- Construction end
- May 13, 2022(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 15, 2021
- Construction end4 months lateforecast Jan 18, 2022
Also in Rimouski