Schedule

Announced and approvedJul 7, 2021
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 12, 2021(actual)
Construction end
Nov 30, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 15, 2021
  • Construction end2 weeks earlyforecast Dec 15, 2021