Port Stanley Public Beach Washroom Renovation
Federal contribution
$146,400
Federal share80%
of $183.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Municipality of Central Elgin
- Construction start
- Aug 23, 2021(actual)
- Construction end
- Jul 15, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast May 15, 2022
Also in Central Elgin