Repair of the exterior facades and entrance awning and roof

Saint-Georges, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$160,000
Federal share75%

of $212.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 1, 2021(actual)
Construction end
Nov 24, 2022(actual)

Also in Saint-Georges

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59034 in the federal list. How to read these figures.