Renovation and upgrading of the domestic water network including the water inlet

Thetford Mines, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$160,000
Federal share80%

of $200.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 28, 2022(actual)
Construction end
Dec 21, 2023(actual)