Replacement of ventilation systems

Drummondville, Quebec

completeVentilationCVRIS
Federal contribution
$640,000
Federal share80%

of $800.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 3, 2022(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 12, 2022
  • Construction end4 months lateforecast Nov 18, 2022