Renovation and upgrading of the sanitary network including grease trap

Saint-Georges, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 27, 2021(actual)
Construction end
Nov 30, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 1, 2021

Also in Saint-Georges