St Stephen Provincial Building - Roof Replacement
Federal contribution
$187,805
Federal share80%
of $234.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Province of New Brunswick
- Construction start
- Apr 8, 2021(actual)
- Construction end
- Aug 24, 2021(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 3, 2021
- Construction end3 months earlyforecast Nov 26, 2021
Also in St. Stephen
- Garcelon Civic Centre$6.2M
- Milltown Boulevard (King Street to Hawthorne Street) - Watermain and Sanitary Sewer Renewal$1.3M
- Elm Park, Pinewood, and Maple - Sewer Separation and Infrastructure Renewal$1.3M
- Combined Sewer Elimination & Water Main Renewal$1.2M
- Combined Sewer Separation and Utility Renewal - Union Street$1.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59297 in the federal list. How to read these figures.