Douglas Carr Trail Extension
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Ingersoll
- Construction start
- Nov 8, 2021(actual)
- Construction end
- Dec 12, 2022(actual)
Against the original forecast
- Construction end7 months lateforecast May 27, 2022
Also in Ingersoll
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59383 in the federal list. How to read these figures.