Little Falls Community Center Roof Repair
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
2022202320242025
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Atikokan
- Construction start
- Oct 1, 2021(actual)
- Construction end
- Dec 17, 2024(actual)
Against the original forecast
- Construction end7 weeks lateforecast Oct 31, 2024
Also in Atikokan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59451 in the federal list. How to read these figures.