Back to projects

Upgrade the Homes Building Automation System (BAS)

Greater Napanee, Ontario

completeVentilationCVRIS
Federal contribution
$38,700
Federal share80%

of $48.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 10, 2021(actual)
Construction end
Sep 20, 2021(actual)

Against the original forecast

  • Construction end5 months lateforecast May 4, 2021

Also in Greater Napanee

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59522 in the federal list. How to read these figures.