Dehumidifier Install in Kenora Recreation Centre
Federal contribution
$182,217
Federal share80%
of $227.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 7, 2021
2022
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Kenora
- Construction start
- May 10, 2021(actual)
- Construction end
- Feb 8, 2022(actual)
Against the original forecast
- Construction end8 weeks lateforecast Dec 17, 2021
Also in Kenora
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59551 in the federal list. How to read these figures.