Town of Milton Community Tree Planting

Milton, Ontario

completeDisaster MitigationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2021
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Milton
Construction start
Oct 1, 2021(actual)
Construction end
Nov 29, 2021(actual)