Boiler replacement

Mirabel, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$190,650
Federal share80%

of $238.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 22, 2021(actual)
Construction end
Jul 5, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 15, 2021
  • Construction end7 months lateforecast Dec 15, 2021

Also in Mirabel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59692 in the federal list. How to read these figures.