Sidewalk and Trail Improvements
Federal contribution
$229,060
Federal share80%
of $286.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Midland
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Aug 17, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2021
- Construction end6 weeks earlyforecast Sep 30, 2022
Also in Midland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59756 in the federal list. How to read these figures.