Back to projects

City of Abbotsford - Barrowtown Pump Station - Backup Power Generator

Abbotsford, British Columbia

completeDisaster MitigationCVRIS
Federal contribution
$5.2M
$5,208,800
Federal share80%

of $6.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 30, 2021
2022202320242025
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Abbotsford
Construction start
Sep 11, 2023(actual)
Construction end
Dec 11, 2024(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jul 17, 2023
  • Construction end3 weeks earlyforecast Dec 31, 2024

Also in Abbotsford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59833 in the federal list. How to read these figures.