City of Abbotsford - Barrowtown Pump Station - Backup Power Generator
Federal contribution
$5.2M
$5,208,800
Federal share80%
of $6.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2021
2022202320242025
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Abbotsford
- Construction start
- Sep 11, 2023(actual)
- Construction end
- Dec 11, 2024(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jul 17, 2023
- Construction end3 weeks earlyforecast Dec 31, 2024
Also in Abbotsford
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59833 in the federal list. How to read these figures.