Replacement of ceiling finishes
Federal contribution
$243,715
Federal share80%
of $304.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de service scolaire de la Seigneurie-des-Mille-Îles
- Construction start
- Jun 13, 2021(actual)
- Construction end
- May 26, 2022(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 15, 2021
- Construction end4 months lateforecast Jan 31, 2022
Also in Mirabel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59879 in the federal list. How to read these figures.