New Cycling Facilities
Federal contribution
$1.8M
$1,804,440
Federal share80%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Corporation of the City of London
- Construction start
- Sep 7, 2021(actual)
- Construction end
- Oct 24, 2022(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Nov 30, 2022
Also in London
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60024 in the federal list. How to read these figures.