Back to projects

Rehabilitation of Town Customer Service Spaces

East Gwillimbury, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$56,000
Federal share80%

of $70.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 9, 2021
20222023
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of East Gwillimbury
Construction start
Jul 3, 2023(actual)
Construction end
Nov 14, 2023(actual)

Against the original forecast

  • Construction start2.2 years lateforecast May 3, 2021
  • Construction end2 weeks lateforecast Oct 30, 2023

Also in East Gwillimbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60025 in the federal list. How to read these figures.