Rehabilitation of Town Customer Service Spaces
Federal contribution
$56,000
Federal share80%
of $70.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
20222023
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of East Gwillimbury
- Construction start
- Jul 3, 2023(actual)
- Construction end
- Nov 14, 2023(actual)
Against the original forecast
- Construction start2.2 years lateforecast May 3, 2021
- Construction end2 weeks lateforecast Oct 30, 2023
Also in East Gwillimbury
- Emergency Medical Services Central Support Facility and Health Connection/Contact Centre$6.5M
- Holland Landing - Yonge St. Revitalization & Multi-Use Path Extension$3.8M
- Garfield Material Recovery Facility Upgrades$2.5M
- East Gwillimbury Watermain Upgrades$2.0M
- Rehabilitation of the existing West Street Sewage Pumping Station to Improve the Efficiency of Wastewater Management$438.4K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60025 in the federal list. How to read these figures.