Rehabilitation of the Vankleek Hill Library
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Champlain
- Construction start
- Sep 13, 2021(actual)
- Construction end
- Nov 18, 2021(actual)