Facility Upgrades FirstOntario Arts Centre Milton
Federal contribution
$103,680
Federal share80%
of $129.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
202220232024
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Milton
- Construction start
- Mar 1, 2022(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Dec 6, 2021