Gibson Street Bridge Replacement
Federal contribution
$186,372
Federal share80%
of $233.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Grimsby
- Construction start
- Nov 18, 2021(actual)
- Construction end
- Jun 7, 2022(actual)
Also in Grimsby
- Baker Road Wastewater Treatment Plant Upgrade$8.3M
- West Niagara YMCA$5.3M
- Grimsby Town Hall Redevelopment/Renovation$2.2M
- Replacement of Main Street and Elm Street Watermains$1.1M
- Water Main Rehabilitation 2021 - Upgrading of Cast Iron Water to PVC including Isolation Valves, Hydrants, and Service Connections$938.5K