Town Hall HVAC Upgrade

Strathroy-Caradoc, Ontario

completeVentilationCVRIS
Federal contribution
$176,878
Federal share80%

of $221.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 9, 2021(actual)
Construction end
Dec 23, 2021(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 21, 2021
  • Construction end8 weeks lateforecast Oct 29, 2021

Also in Strathroy-Caradoc