Ellor St replacement of 250 mm sanitary sewer, upgrade of watermain to 150 mm and new 900 mm Storm Sewer for separation

Strathroy-Caradoc, Ontario

completeWastewaterCWWF
Federal contribution
$180,106
Federal share15%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 4, 2017(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start15 months lateforecast Apr 1, 2016
  • Construction end4 months lateforecast May 31, 2018